An RFQ that states fixed, TBD and maker-proposed inputs lets the supplier answer with a matching model and drawing.
A transformer bushing RFQ has to state four things: the electrical duty, what is on each side of the bushing and how the current passes through it, the interface drawing, and the site conditions. Add the standard edition and the test limits you will accept, and mark every value you don't know yet as TBD instead of guessing it.
- Electrical duty: Um, frequency, rated current with the transformer's overload, and the insulation levels as one set.
- Media and conductor: oil–air, GIS, oil–SF6 or oil–oil, and draw-lead or bottom-connected.
- Interface drawing: flange, CT pocket, oil-side length and terminals, with the drawing revision.
- Site conditions: altitude, ambient, pollution, mounting angle, seismic level.
- Documents: standard and edition, PD limits with their test voltage and stage, tan δ limits, reports per unit.
We make dry-type condenser bushings for transformers, reactors, GIS and wall duty.
What a bushing RFQ has to carry, and how to mark what you don't know yet
Keith Ellis's handbook Bushings for Power Transformers (2011) sums up what a bushing specification needs: the standard editions, the site duty, any construction preferences, the interface dimensions and the documents you expect. He also warns that latest revision in an old sample specification does not tell anyone which edition governs today, so name it.
| Group | What it fixes | Typical source |
|---|---|---|
| Electrical duty | Voltage class, current, test levels | Transformer design data |
| Media and conductor | Bushing family and current path | Transformer and GIS layout |
| Interface drawing | Whether it fits the tank | Turret and flange drawing |
| Site conditions | External insulation and special design | Site survey, project spec |
| Documents | What proves the design and each unit | Project or utility spec |
Each line needs a status as well as a value. Use one of three:
- Fixed: the value is final and the drawing will be made to it.
- TBD, with owner: the value is still open; say who will confirm it (design, site, end client).
- Maker to propose: you attach the drawing or data and ask the maker to work the value out.
Lines the maker can work out, and what to attach
Some values you don't have to decide yourself, as long as you send what they are worked out from:
| Line | Attach this | The maker works out |
|---|---|---|
| Bushing current | Transformer current and overload | Current rating with margin |
| Oil-side length, shield, CT pocket fit | Turret and CT drawing | Length and fit |
| Creepage | Site pollution class | Creepage for that class |
| Conductor arrangement | Winding-lead detail | Draw-lead or bottom-connected |
Other lines have to come from you: Um (the highest voltage the bushing is designed for) and the insulation levels, the standard and its edition, and the site values. The insulation levels come from your insulation coordination, the study by the transformer or system designer that sets how much surge and test voltage each piece of equipment must withstand. A maker can't infer those, and a guess there changes the bushing.
Two rules from our side explain why this helps. A family range in our handbook does not mean every voltage and current pair inside it exists as a drawn model, so the RFQ has to state your actual pair. And on special projects the technical agreement and the confirmed drawing govern over our general guides, so whatever you mark as fixed is what the drawing will be built to.
If you are designing a new transformer and the turret (the raised flange on the tank cover that the bushing bolts onto) is not frozen yet, send the RFQ anyway with those lines marked TBD; the maker can start on the electrical side. If you are replacing a bushing in service, every interface value already exists on the tank, so measure it rather than guess. The transformer bushing selection guide helps if you still have to choose the family.
Electrical duty: Um, current with overload, and the insulation levels as one set
Write Um, the system frequency, the rated current with the transformer current and its overload, the short-time withstand current, and the insulation levels from your insulation coordination.
Um is the highest voltage for equipment: the top of the voltage range the bushing is designed for, not the nominal network voltage; the transformer bushing selection guide shows how it is picked. The frequency belongs in the RFQ too. IEC 60137:2017 applies to bushings used on three-phase AC equipment rated above 1,000 V and running at 15 to 60 Hz, so state your system frequency.2
Write the insulation levels as one set
Lightning-impulse withstand (often called BIL) is the surge level; power-frequency withstand is the one-minute AC test; switching-impulse withstand is a third level that your coordination study specifies at the higher voltage classes. Write all of them as one set. Our handbook's table for RIF transformer bushings (RIF is a dry condenser core made of resin-impregnated fibre) shows what a complete set looks like:
| Um (kV) | One-minute AC withstand (kV) | Lightning impulse (kV) | Switching impulse (kV) |
|---|---|---|---|
| 123/126 | 255 | 550 | — |
| 245/252 | 505 | 1050 | 850 |
| 550 | 750 | 1675 | 1300 |
Read the table as three numbers that belong together for each Um. In our tables a switching-impulse value only appears from the 245/252 kV row up; whether your bushing needs one is set by your coordination study, not by our table. If your study asks for different levels, write yours.
Write all the numbers, not only Um. Ellis makes the point that a bushing with enough continuous voltage capability can still have too low a BIL for the winding it serves.
Give the transformer current, overload and short-time current
Give the transformer's rated current at that terminal and its overload requirement, then the bushing current you expect. A 2022 CIGRE paper (A2-10131) reports that IEC 60137 treats a bushing rated at no less than 120% of the transformer rated current as able to carry the loading-guide overloads without further checks. The same paper notes the rule rests on experience and daily average temperatures and does not cover short peaks in the load curve, so a cyclic or peaky duty belongs in the RFQ.
Add the short-time withstand current, its duration and the peak current, taken from the system fault level in your substation study. They decide the conductor's thermal and mechanical withstand, and leaving them out means the maker has to assume them.
Our oil–air transformer bushing family spans Um 12–550 kV and 630–8,000 A, but that is a family range, not a list of models: state the Um and current pair you need and the maker answers with the row that fits. The bushing product families show the ranges.
Say what is on each side and how the current gets through
Name the medium on each side of the bushing, or its duty; that picks the family. Then say whether it is draw-lead or bottom-connected, with the lead size or the lower terminal form, and which air-side terminal you need.
Media on each side decide the family
| What is on each side | Family to ask for |
|---|---|
| Transformer oil and outdoor air | Oil–air transformer bushing |
| GIS gas and outdoor air | GIS bushing |
| Transformer oil and SF6 | Oil–SF6 bushing |
| Oil on both sides | Oil–oil bushing |
| A wall or building penetration | Wall bushing |
| Very high current at medium voltage | High-current bushing |
GIS and oil–SF6 bushings are the pair buyers mix up, because both touch SF6. Our drawings keep them apart: GIS bushings are marked air side and GIS side, while oil–SF6 bushings are marked SF6 side and oil side. Writing only SF6 bushing in an RFQ leaves the maker guessing; the GIS bushing vs oil–SF6 bushing guide explains the difference.
Wall bushings are a separate family, 12–550 kV and 630–5,000 A in our handbook. So are high-current bushings: the handbook overview runs to 40,000 A, but the named selection rows stop at 31,500 A, so a higher figure needs a drawing check rather than a catalogue pick.
Draw-lead or bottom-connected
Our oil–air transformer bushings are listed separately as draw-lead and bottom-connected types, each with composite or porcelain housings.
- Draw-lead: the transformer's winding lead is pulled up through the bushing's central tube and connected at the top. State the lead size and the top terminal you need. Our draw-lead heads come in a threaded locking design and a plug-in locking-pin design.
- Bottom-connected: the bushing's own conductor carries the current and the winding lead bolts to a lower terminal. State the lower terminal form you need; Ellis lists threaded studs, spades and plates as the usual forms.
The two carry current differently. Wagenaar's bushing chapter in Harlow's Electric Power Transformer Engineering (2007) separates the bushing's own current rating from the rating of a lead drawn through it, which is why a draw-lead RFQ needs the lead size and not only a bushing current.
For a new design, the transformer bushing selection guide compares the two arrangements; if you are still not sure which suits your winding, send the lead detail and ask the maker to propose one. For a replacement, keep the arrangement and terminal of the bushing you are taking out; changing it changes the current path and the connection work inside the tank.
Send the interface drawing: flange, CT pocket, oil-side length and terminals
Send the turret and flange drawing with its revision number. A bushing with the right ratings can still fail to fit, and the drawing is where fit is decided.
| Dimension | Where it comes from |
|---|---|
| Flange bolt circle, hole count and size | Turret drawing |
| Sealing face and gasket | Turret drawing |
| Body diameter below the flange | Turret and CT inner diameter |
| CT pocket length | Stacked height of CTs and spacers |
| Oil-side length | Tank and winding clearances |
| Air-side height and top terminal | Outdoor layout and connections |
The turret is the raised flange on the tank cover that the bushing bolts onto; the CT pocket is the section below the flange where bushing current transformers sit. Wagenaar treats the pocket length, clearances and mounting details as interface data in their own right.
For a replacement, Ellis treats the length below the flange, the CT pocket length and the body diameter as three separate checks, and says a matching voltage and current rating does not settle any of them. The part above the flange matters too: a new bushing that is taller or shorter can change the buswork, the phase and ground clearances, the draw-lead length and the distance to the surge arrester. So for a replacement, add the old nameplate, the original drawing if you have it, and measured dimensions.
Two notes from our side. Our handbook's dimensions are references, and the drawing we issue for your order is the one that governs, so ask for a confirmed outline drawing with the quote and check it against your turret. And for one of our stress-shield designs (the bolted type), the guide requires the total oil-end length to be measured after assembly and checked against that outline drawing.
How each of these dimensions affects the choice of bushing is covered in the transformer bushing selection guide. If the turret or the CT stack is not frozen yet, list those lines as TBD in the worksheet below rather than sending a provisional dimension as final.
Site conditions that change the design
Give the site's minimum and maximum ambient, altitude, pollution level or required creepage, mounting angle, any seismic standard and level, and for gas-side bushings the gas and its pressure. Then compare them with the maker's stated service conditions: anything outside them changes the drawing.
Here are ours, so you can see where a site falls outside:
| Condition | Our stated condition | What to put in the RFQ |
|---|---|---|
| Ambient temperature | −50 °C to 55 °C | Site minimum and maximum |
| Altitude | 1,000 m | Site altitude |
| Mounting angle (transformer) | 0° to 60° | Actual angle |
| Oil temperature | 90 °C daily average, 115 °C short-time | Your overload oil temperatures |
| SF6 pressure (GIS) | 0.45–0.6 MPa rated, 0.8 MPa maximum | GIS rated and maximum pressure |
| Pollution | Class IV (GIS guide) | Site class or required creepage |
| Seismic | Not in the stated conditions | Standard and level, if any |
The ambient range is from our transformer bushing guide, as are the 0°–60° mounting angle, with steeper angles possible as a special design, and the oil temperatures. The GIS guide states 1,000 m and, above that, corrects the design to the standard and the project requirements. The GIS guide adds the SF6 pressures, vertical or inclined mounting with inverted mounting as a special design, and pollution class IV.
Creepage distance is the path along the outer insulation surface; a dirtier site needs a longer one. The creepage distance and altitude guide explains how both are worked out, and what each condition means for selection is in the transformer bushing selection guide.
Beyond the table, Ellis lists the unusual conditions worth declaring: pollution, wetting and icing, corrosive or explosive air, vibration and shock, mobile transformers, bus-duct heat, poor ventilation, fire-deluge wetting, and storage and transport. He is clear these are questions for the maker, not proof that any bushing suits them.
A few lines only apply to some projects; add them when yours has them. If the transformer is filled with natural or synthetic ester rather than mineral oil, say so. If the terminals carry heavy busbar or conductor loads, give the cantilever load, the sideways force on the top terminal. And give the tank's vacuum and pressure conditions during filling, since the bushing's oil end sees them too.
Seismic needs its own line. Ellis also notes that the housing material alone does not make an assembly seismically qualified, so if your project has a seismic specification, name the standard and the level in the RFQ. Added after the drawing is approved, it can mean a new check or a separately priced test.
Name the standard and edition, and write test limits you can check
Name the standard with its edition, list the tests and reports you need, and write each acceptance limit with its stage, plus the test voltage for partial discharge. A PD limit without its voltage cannot be checked, and an installation guide is not a test report.
Standard and edition
IEC 60137 is the international bushing standard. The IEC catalogue lists edition 7.0 (2017) with its 2018 corrigendum as valid, with edition 8.0 in development, so write IEC 60137:2017 rather than latest edition.3 In IEEE markets, IEEE C57.19.00-2023 applies to liquid-immersed transformer and reactor bushings above 110 kV BIL,4 and its scope leaves out, among others, bushings with an external gas other than air,4 so check which standard covers a GIS or oil–SF6 bushing before you name one. Add any national standard your utility requires.
Write limits with voltage and stage
Partial discharge (PD) is a tiny internal discharge measured in picocoulombs (pC); tan δ is the dielectric loss of the insulation. Our handbook lists two dry condenser cores separately: RIF, made of resin-impregnated fibre, and RIP, made of resin-impregnated paper; the offered model and datasheet say which one you are buying. The same PD figure means different things at different voltages and stages, and the factory measuring voltage depends on the core:
| Where the limit applies | PD limit | PD test voltage | tan δ limit |
|---|---|---|---|
| Factory, RIF transformer bushings | 10 pC max | Um | 0.4% max |
| Factory, RIP transformer bushings | 10 pC max | 1.5 Um/√3 | 0.6% max |
| Factory, GIS bushings | 5 pC max | 1.2 Um/√3 | — |
| Site handover, transformer bushings | 10 pC max | 1.5 Um/√3 | — |
So RIP bushings have their PD measured at a lower voltage than RIF ones, GIS bushings at their own PD voltage, and the site PD test at its own voltage again. The tan δ figures are limits only; the handbook gives no separate test voltage for them. At site handover the transformer guide also applies the AC withstand at 85% of the factory test voltage. Write your limit the same way, for example: PD 10 pC max at 1.5 Um/√3, site handover test.
State the site steps you expect too. For transformer bushings, our guide sets 6–24 h of standing after conventional oil filling before energising, with no wait after vacuum filling.
Ask for the documents themselves
A type test proves the design once; a routine test checks every bushing before it leaves the factory. Ask for the type-test report that matches the offered model, a routine record per serial number, and say which tests your inspector wants to witness and which special tests (seismic, for example) you need. The test tap, the small terminal used to measure capacitance, tan δ and PD in service, belongs on the list if you plan to monitor the bushings.
An installation and maintenance guide is general guidance, not a type-test report for a model, so ask for the reports. Our Downloads page states that routine test reports accompany deliveries, and lists our CTQC type-test reports (including English editions) available on request at /downloads/.1 How to read each report is covered in type tests vs routine tests; comparing site readings with factory values is in reading capacitance and tan delta, and online monitoring in smart bushing condition monitoring.
A worksheet you can copy into your RFQ
Put every line in one worksheet. Required lines are what a maker needs to propose a model and drawing; If applicable lines depend on your project. Give each line a status and say who confirms it.
| Line | Need | Your value | Status, confirmed by |
|---|---|---|---|
| Family (media on each side) or duty | Required | Fixed / TBD / maker to propose | |
| Um, frequency | Required | ||
| Rated current, transformer current and overload | Required | ||
| Short-time current, duration and peak | Required | ||
| Lightning and AC withstand | Required | ||
| Switching-impulse withstand | If applicable | Use the level specified by your insulation coordination. Enter N/A if the study specifies no switching-impulse level. | |
| Conductor arrangement, lead size, terminals | Required | ||
| Flange, sealing face, body diameter | Required | ||
| CT pocket length, oil-side length, air-side height | Required | ||
| Drawing number and revision | Required | ||
| Ambient, altitude, pollution or creepage | Required | ||
| Mounting angle | Required | ||
| Oil temperatures, daily average and overload | Required | ||
| Insulating liquid, if not mineral oil | If applicable | ||
| Tank vacuum and pressure during filling | If applicable | ||
| Gas and pressure (gas-side bushings) | If applicable | ||
| Seismic standard and level | If applicable | ||
| Cantilever load, special terminal loads | If applicable | ||
| Standard and edition | Required | ||
| PD limit with test voltage and stage | Required | ||
| tan δ limit and stage | Required | ||
| Reports and witness tests | Required | ||
| Special tests (seismic or others) | If applicable | ||
| Test tap and monitoring provision | If applicable | ||
| Quantity, spares, accessories | Required | ||
| Delivery destination | Required |
On the commercial side, standard factory turnaround times are clearly scheduled by core insulation technology: 4 weeks for RIF (resin-impregnated synthetic fiber, 12kV–252kV, including full routine electrical testing), 6–8 weeks for RIP (resin-impregnated paper, 12kV–252kV, including full routine testing), and custom scheduling based on individual drawing reviews for 550kV extra-high voltage or high-current generator applications. Minimum order quantities, sea/air export packaging, and payment terms are confirmed per specific project quantity and destination requirements. Spares belong on the list too: our transformer bushings come with a vent-plug gasket and an O-ring under the top cover as standard spare parts, and anything beyond that is a line to add.
When you compare offers from more than one maker, ask each to state what is included (bushings, spares, reports, witness tests) and what is priced separately. Offers that look cheaper often leave something out.
What to ask for in the reply
Ask the reply to come back in a form you can check against your worksheet, line by line:
- The offered model and the family it belongs to.
- A filled datasheet answering each RFQ line, with the maker's value next to yours.
- A preliminary outline drawing with its number and revision.
- The standard and edition the bushing is designed and tested to.
- A list of deviations and assumptions, numbered against your RFQ lines, instead of a single complies statement.
- The reports: the matching type-test report and a routine record for each serial number you will receive.
For the rest of the paperwork, Ellis's documentation list works well: how the bushing is built, routine reports, nameplate data, receiving and cleaning, installation and commissioning, how to store it, what to test in the field, and how much measured values may change. He adds that the list only works once you know what you actually require and what evidence comes with each delivered serial number.
Check the outline drawing against your turret before you approve it (the issued drawing governs, as explained above), then put the approved drawing number, its revision and the model on the purchase order. The product families page shows what each family covers.
Fix the lines, flag the unknowns, then approve the drawing
A bushing RFQ works when it carries the electrical duty, the media and conductor arrangement, the interface drawing and the site conditions, plus the standard edition and PD limits written with their test voltage. Fix the values you know, mark the rest TBD with an owner, and attach the turret drawing. When the reply arrives, check the datasheet, the deviations and the outline drawing against the same worksheet before you approve anything.
Submit Your Bushing Requirements
Send your RFQ worksheet details and drawing references, and we will propose a model and drawing for your duty.
More guides are in the bushing knowledge hub.
References
- ZLVOLT Downloads page (company website)
- IEC 60137:2017 — Insulated bushings for alternating voltages above 1 000 V (IEC webstore public page) — 2017-06-22
- IEC 60137 catalogue status: edition 7.0 (2017) and 2018 corrigendum valid, edition 8.0 in development — 2017-06-22
- IEEE Std C57.19.00-2023 — General Requirements and Test Procedure for Power Apparatus Bushings (IEEE Xplore abstract) — 2023-05-15
How this guide was prepared: Prepared by ZLVOLT engineering from our dry-type bushing handbook, our transformer and GIS bushing installation guides (Q/ZL-JS-501-2026 and Q/ZL-JS-502-2026), and the standards and references listed above. The confirmed drawing and the project technical agreement decide the final design. Content date: November 2026.