Illustrative external forms for different media interfaces; the required media pair determines the family.
Both bushings have one end in the SF6 gas of gas-insulated switchgear (GIS), so look at the other end. Air on the other end means a GIS bushing. Transformer oil on the other end means an oil-to-SF6 bushing.
A GIS bushing takes the switchgear's gas out to air, for example toward an overhead line. An oil-to-SF6 bushing joins a transformer straight into the GIS, with no air section in between. This guide shows how to read that from the layout and the drawing. It then covers what each end, the gas and the specification have to match. It applies to bushings at the GIS boundary; oil-to-air and oil-to-oil transformer bushings are other families.
- Check the medium on the end that is not in SF6. That end names the family.
- Confirm it on the drawing: a GIS bushing is marked air side and GIS side, an oil-to-SF6 bushing SF6 side and oil side.
- Match each end to the drawing of the equipment it bolts to, not to a catalogue table.
- Take pressure, mounting and site conditions from the chosen family's own documents.
- Cite IEC 60137 for both families, and add IEC 62271-211 for an oil-to-SF6 bushing.
Tell them apart by the medium on the other end
Look at what the non-SF6 end sits in. If it is outdoor air, you need a GIS bushing. If it is transformer oil, and the transformer connects straight into the GIS, you need an oil-to-SF6 bushing.
GIS is switchgear sealed in metal enclosures filled with SF6 gas. Both families have one end in that gas. So "SF6 bushing" on an enquiry does not name either one.
Our handbook keeps the two apart on the drawings. A GIS bushing drawing labels its ends "air side" and "GIS side". It is listed as an air-to-GIS-gas connection, separate from the oil-to-SF6 bushing. The oil-to-SF6 page labels its ends "SF6 side" and "oil side".
You can also see the difference on the outside. An air end needs sheds, the ribbed skirts that lengthen the surface path along the insulator. That path is the creepage distance, and it has to suit the site's pollution. SF6 insulates far better than air, so the SF6 end needs no long creepage. That is why an oil-to-SF6 bushing has no sheds and is much more compact than an oil-to-air bushing.
| Check item | GIS bushing | Oil-to-SF6 bushing |
|---|---|---|
| Media joined | GIS gas to air | Transformer oil to GIS gas |
| Drawing end labels | Air side / GIS side | SF6 side / oil side |
| Sheds on the outside | Yes, on the air end | None; compact SF6 end |
| Series prefix in our range | FGRG / EGRG; FGRGL / EGRGL | YQRGL |
| Service conditions from | Our GIS guide and the drawing | The offered model's drawing and agreement |
In our model coding, FGRG and EGRG denote GIS bushings—F for composite silicone-rubber external insulation and E for porcelain. The handbook selection tables list FGRGL and EGRGL. An L in the prefix marks a reserved current-transformer (CT) position. A CT is the ring sensor that measures current around the conductor, so a model with L and one without are not interchangeable.
For oil-to-SF6 bushings, the handbook uses YQRGL. Earlier materials sometimes used YQBRGL; we corrected that to YQRGL, so you may still meet the old name in older documents. Because both ends of an oil-to-SF6 bushing are enclosed—one in transformer oil, the other in the GIS gas compartment—there is no atmospheric-side shed body, and the prefix has only one series.
Order against the drawing number and revision, not the prefix alone.
If the labels, the prefix and the plant layout do not agree, hold the order. Confirm the drawing number and revision first. A prefix or a catalogue table cannot settle a conflict with the actual layout.
For product details, see our GIS bushings for gas-to-air connections and our oil-to-SF6 bushings for direct transformer-to-GIS connections.
Where each bushing sits, and what each end connects to
A GIS bushing sits on the GIS, where the switchgear leaves its gas enclosure and continues in air. The air end then connects on, for example to an overhead line.
An oil-to-SF6 bushing sits between the transformer tank and the GIS enclosure. It is used where the transformer connects directly to the GIS busbar or switchgear. There is no air section in between, so there is no place for a GIS bushing at that point.
This direct transformer–GIS connection has its own interface standard. IEC 62271-211 covers direct connections between a transformer and GIS above 52 kV. It is the standard that frames who supplies what at that joint.
Some oil-to-SF6 designs can be mounted horizontally. That can lower the height of the connection structure. Treat a published plant layout as one example, though. It is not the arrangement every project uses. Your own single-line diagram and layout drawing decide where each bushing goes.
A quick test on your layout: follow the conductor from the transformer. If it goes into a GIS enclosure without passing through air, that joint needs an oil-to-SF6 bushing. If the GIS later sends the circuit out to an overhead line, that exit needs a GIS bushing. One substation can need both.
If your connection is oil to air or oil to oil instead, see transformer bushing selection by connection media.
What each end has to match on the drawing
Match each end to the drawing of the equipment it bolts to. Our handbook dimension tables are references; the issued drawing governs. The same goes for ratings: ask for the specific row that fits your voltage and current, not the family range.
GIS bushing: GIS-side flange and air side
The GIS-side flange and seal faces have to fit the GIS maker's enclosure drawing. The air end follows the line connection and the creepage the site needs.
The terminal is chosen from the GIS terminal table by rated current, from 2,000 A to 5,000 A. The drawing shows where it sits.
Say whether a CT goes on the bushing. An L in the prefix marks a reserved CT position. Our GIS bushing guide also asks a new project to state its ratings, altitude, pollution class, housing type (porcelain or composite) and the reserved CT height.
Oil-to-SF6 bushing: SF6-side flange and oil side
The SF6-side flange has to fit the GIS drawing, just as on a GIS bushing. The oil end has to fit the transformer turret, the raised housing on the tank that the bushing mounts into.
The handbook gives an oil-to-SF6 terminal table by rated current, from 1,600 A to 4,000 A, and a separate flange-attachment table by rated voltage. The drawing places the terminal. If the prefix has an L, state the CT you need for the reserved position.
When the transformer and the GIS come from different makers, this joint has two owners. IEC 62271-211 deals with interchangeability and the supply boundary at the direct connection, for GIS above 52 kV. Use it to agree who supplies which part of the interface.
Ratings: ask for the row, not the range
Our handbook family-overview table lists GIS bushings at 40.5 kV to 550 kV and 630 A to 8,000 A, and oil-to-SF6 bushings at 40.5 kV to 550 kV and 630 A to 4,000 A. But the overview range does not mean every voltage and current combination has a drawn and type-tested model.
What you can order is a selection-table row. The handbook GIS bushing selection tables (FGRGL and EGRGL) list models from 72.5 kV to 550 kV, with rated-current steps of 2,000, 3,150, 4,000 and 5,000 A. The oil-to-SF6 table (YQRGL) lists rows at 72.5, 126, 252, 363 and 550 kV, with current rows including 630, 1,250, 2,500 and 3,150 A; the matching terminal table covers 1,600 A to 4,000 A.
Give your system voltage and rated current, and ask for the row that matches both.
Two habits save the most trouble here.
First, get the GIS maker's interface drawing before you freeze the bushing order. This matters most when the transformer and the GIS come from different suppliers. Ask the GIS supplier for the flange and seal-face drawing, with its revision, and send it with your enquiry. It avoids a re-drawn flange or a site adapter after the bushing is built.
Second, put the drawing number and revision on the purchase order, not just the series prefix. Old and new prefixes and documents are both in circulation. Copying the number from the approved drawing avoids receiving a bushing built to an older or different drawing.
For the full list of what to send with an enquiry, see our bushing RFQ inputs.
State the gas, pressure and mounting for the family you chose
Take the gas, pressure, mounting angle and site conditions from the chosen family's own documents. Values written for one family do not carry over to the other.
GIS bushing: conditions in our installation guide
Our GIS bushing guide states these service conditions:
- SF6 on the GIS enclosure side: rated pressure 0.45–0.6 MPa, maximum pressure 0.8 MPa.
- Mounting: vertical or inclined; inverted mounting needs a special design.
- Ambient temperature: −50 °C to 55 °C.
- Altitude: up to 1,000 m; above that, correction follows the standard and the project requirements.
- Pollution: class IV.
Rated pressure and maximum pressure are different numbers. The rated value is the normal filling; the maximum is the ceiling. State both.
Where a special project has its own agreement, the agreement and the confirmed drawing govern. These are general installation-guide values, not a type-test report for a specific model.
If your site is above 1,000 m, see creepage and altitude correction.
Oil-to-SF6 bushing: take conditions from the offered model
The values above belong to GIS bushings. Do not copy them into an oil-to-SF6 enquiry. Take the oil-to-SF6 pressure, mounting angle and ambient range from the offered model's drawing and the project agreement.
Name the gas, and watch the oil–gas seal
Write the insulating gas by name in the enquiry, even when it is the usual gas. This matters when the GIS supplier offers alternative gases or mixtures. Add the gas or mixture name and the GIS supplier's filling pressure. It avoids a bushing quoted for a gas the GIS will not use.
The 2024 revision of IEC 62271-211 covers gas tightness and pressure provisions for SF6, other gases and mixtures. Compatibility of a given bushing with a given alternative gas needs its own evidence, so ask for it by name.
An oil-to-SF6 bushing also seals transformer oil from GIS gas. A dry core, meaning the bushing's insulation is resin-impregnated with no oil filling inside, does not change that: the connected equipment still holds oil and SF6, and the seal is not a zero-leak guarantee.
Doble, a maker of transformer test and monitoring equipment, notes that GIS gas seals can develop leaks over time. It asks how you would know if SF6 leaked through a bushing seal into the transformer tank. DGA is dissolved-gas analysis, the oil test that flags faults inside a transformer. Doble reports that about 0.3% of oil samples in its North American DGA laboratories contain traces of dissolved SF6, and it expects more where GIS is common.
Doble also notes that dissolved SF6 can make some infrared-based DGA monitors read falsely high.
So tell the transformer owner's gas-analysis team that the tank has an oil-to-SF6 interface. Note it in the monitoring records. Then an unusual reading gets checked against a possible seal leak, instead of being taken for an internal transformer fault.
Name the standard that covers each interface
Cite IEC 60137 for both families. For an oil-to-SF6 bushing, add IEC 62271-211 for the joint between transformer and GIS; one standard alone can leave that gas end without an agreed requirement.
- IEC 60137 is the bushing standard. It covers separately supplied bushings for AC equipment above 1,000 V, at 15 Hz to 60 Hz.
- IEC 62271-211 is the interface standard for the oil-to-SF6 case. It covers the direct transformer–GIS connection for GIS above 52 kV.
- IEEE C57.19.00 covers liquid-immersed transformer and reactor bushings with a BIL above 110 kV. BIL is the lightning impulse voltage the insulation is rated to withstand. Its scope excludes external gas other than atmospheric air.
That last point is the trap. A specification for an oil-to-SF6 bushing that cites only IEEE C57.19.00 leaves the gas end outside the cited scope. Add IEC 62271-211 for the joint between transformer and GIS.
Once the standards are named, the next question is which report covers this exact family and interface. See what type-test and routine-test reports prove.
The non-SF6 end decides the family; the drawings decide the order
Air on the other end means a GIS bushing. Transformer oil on the other end means an oil-to-SF6 bushing. That settles the family.
The order is settled by the rest: each end matched to its mating drawing, service conditions taken from the chosen family's documents, the gas named, and IEC 60137 cited, plus IEC 62271-211 for an oil-to-SF6 bushing. If any of those is still open, keep the order provisional until it is confirmed.
If your connection turns out not to be at the GIS boundary, browse all bushing families or more bushing guides.
Review the Relevant Bushing Options
Compare our oil-to-SF6 bushings for direct transformer-to-GIS connections and our GIS bushings for gas-to-air connections, or send your interface drawings for review.
References
- Doble Engineering, 'Is SF6 Dissolved in Your Transformer Oil?', blog, 2020 — 2020-02-27
- IEC 60137:2017, Insulated bushings for alternating voltages above 1 000 V — 2017-06-22
- IEC 62271-211:2024, Direct connection between power transformers and GIS for rated voltages above 52 kV — 2024-09-04
- IEC 62271-211:2024 revision summary: gas and vacuum tightness, other gases and mixtures — 2024-09-04
- IEEE Std C57.19.00-2023, General Requirements and Test Procedure for Power Apparatus Bushings — 2023-05-15
- M. J. Heathcote, The J & P Transformer Book, 12th ed., Newnes, 1998, §4.8 'SF6 connections' — 1998
How this guide was prepared
Prepared by ZLVOLT engineering from our dry-type bushing handbook, our GIS bushing installation and maintenance guide (Q/ZL-JS-502-2026) and the standards and references listed above. The confirmed drawing and the project technical agreement govern the final design. Content date: November 2026.